Historical same-site roof and ground-mount estimates
Roof-mounted versus ground-mounted solar proposals for a new build
The same new build received two estimates: $48,890 for a 24-panel ground mount with trenching and $58,950 for a 38-panel rooftop design. Each used different modules, power conversion and storage. There were no electricity bills for the new home, so neither quote can establish a usage offset.
- 24 Jinko 540 W modules and one EG4 battery
- 12.96 kW DC ground
- 38 Jinko 425 W modules and one FranklinWH battery
- 16.15 kW DC roof
- Separate gross prices for the two alternatives
- $48,890 versus $58,950
What equipment and work change when the array moves?
| Component | Ground option | Roof option |
|---|---|---|
| PV modules | 24 JinkoSolar JKM540M-72HL4-V modules at 540 W. Exact 12.96 kW DC. | 38 JinkoSolar JKM425N-54HL4 modules at 425 W. 16.15 kW by multiplication; approximately 16.1 kW as quoted. |
| Power conversion | One EG4 FlexBOSS21 hybrid inverter listed at 16 kW. | 38 Enphase IQ8HC-72-M-INT microinverters, one per module. Aggregate AC rating listed as 14.44 kW. Neither rating is a verified utility export limit. |
| Battery storage | One EG4 PowerPro WallMount unit, 14.3 kWh listed. | One FranklinWH aPower 2 AC-coupled unit, 15 kWh listed. |
| Mounting and site work | Fixed-tilt ground rack, posts or anchors, rails and clamps; trenching from the array to service equipment. Final footing type and trench length not set. | Rails, clamps, roof flashings and bonding materials. Roof facets, clearances and exact roof layout needed field verification. |
| Controls and startup | EG4 monitoring setup, electrical integration and commissioning checks. | Enphase combiner, Franklin gateway, app setup, electrical integration and commissioning checks. |
| Estimated year-one production | 18,172 kWh as quoted. | 23,382 kWh as quoted. |
| Gross quote | $48,890 on August 19, 2025. | $58,950 on August 15, 2025. |
The $10,060 price difference is for two different designs. It is not a generic rule that ground mounts cost less or a line-item comparison for moving the same exact equipment.
What did the proposals leave for the site visit?
- Verify ground space and trench route. The ground plan assumed space for a fixed-tilt rack. It included trenching, but the route and length were not fixed. The document contemplated expansion subject to future site and electrical design.
- Check the new roof and access needs. The roof option assumed it could fit the proposed panel layout while clearing roof features and future service paths. No current aerial imagery was available for the new build; the layout still required a field review.
- Review actual loads before agreeing to production or backup conclusions. Without a year's utility use, neither quote can establish annual offset or return on investment. The battery figures are the listed energy storage, not a promise that a selected circuit will run for a particular duration.
What evidence can a buyer compare here?
| Item | Evidence |
|---|---|
| Energy | Both sources print a modeled annual generation estimate. Neither contains a site-specific month-by-month production or bill table. The numbers are not measured output. |
| Pricing | Both quotes are gross scopes for one site and neither is signed or verified paid. No validated incentive is deducted. |
| Installation | No chosen option, final quote, exact as-built site layout, startup report or approved property photos were verified. |
| Source matching | Customer and property fields on both files match. One draft title contains a conflicting address number, so all street information is withheld. |
Ask whether roof or ground is better for your property
Compare available shade-free area, final mounting layout, trenching and equipment access, then look at the price and backup design together.
Request a roof-versus-ground solar assessmentSource: Anonymized The Metal Roofers August 15 and August 19, 2025 same-property estimates. Prices and production are historical estimates, not an installed result.

