Roof and solar coordination · Closed and paid project
Removing and reinstalling 15 solar panels, then adding five
An existing solar array needed to move for roof work. The signed scope called for taking down 15 panels, reinstalling them on the completed lower roof section, and adding five panels while the array was open. The solar contract was $8,925 and both invoices were paid. The roofing was a separate scope.
- Existing panels in the removal and reinstallation scope
- 15 panels
- Signed design count with five additional modules
- 20 panels total
- Two recorded payments for the solar scope
- $8,925 paid
What had to happen before the panels could go back?
The contract specified a finished, watertight lower roof ready for new racking footings before scheduled solar work. The roofing contractor was responsible for that work. The solar estimate assumed one workday for removing and reinstalling the equipment; that was a pricing assumption, not a verified on-site duration.
- Document the existing system before taking it offline. The scope called for an installer to check the existing system and record the operating baseline before removal.
- Take down the 15 existing modules. The contract included temporarily removing the panels and detaching the wiring, conduit and related components as needed for roof access.
- Check the old rack and install new footings. The solar crew was to supply and install new footings on the completed roof. Reuse of the existing racking was anticipated, subject to inspection once removed. If it could not be reused, replacement required a written change order.
- Reinstall the 15 existing modules and add five. Reconnecting the wiring and conduit was in scope. The agreement called for 20 panels total, but did not state the individual panel model, wattage or resulting system size in kW.
- Reenergize and compare operation with the baseline. The contract included an installer test after the reset. The actual baseline and final measurement were not available in the records used here.
Why the roof handoff mattered: A solar crew cannot reset the panels on an unfinished roof. The agreement kept the roof work and solar work separate and required a written change order for additional trips or other work outside the one-day assumption.
What did the solar removal and reinstallation cost?
The signed August 31, 2026 price included the 15-panel removal and reset, new footings, five additional panels, reconnecting the wiring and conduit, and the specified testing. The agreement noted that a $975 increase covered three of the five new panels and the company absorbed the cost of the other two. That is this contract's price adjustment, not a published unit price.
| Invoice | Amount | Record |
|---|---|---|
| Deposit | $4,462.50 | Paid; due at signing under the agreement |
| Final payment | $4,462.50 | Paid; due at final completion and system testing under the agreement |
| Total paid | $8,925.00 | Balance: $0 |
Roofing work and replacement of unusable existing racking were not included in this sum. The signed agreement was prepared for insurance submission, but the record does not establish insurance approval, reimbursement or a covered amount.
What was covered, and what do the records verify?
| Topic | What the records support |
|---|---|
| Job and payment | Closed and paid. The signed agreement and both paid invoices support the $8,925 solar project total. |
| Equipment | Fifteen existing panels plus five new units under the agreement. Wattage, module model, inverter model, final array kW and an independently verified as-built count are not available. |
| Testing | The scope included an operating check before removal and after reconnecting the array. A paid final invoice does not establish the test values, additional energy production or utility approval. |
| Workmanship | This agreement specified a two-year workmanship warranty on the company's removal, new footings, rack reset, reinstallation and reconnections. It did not warrant the existing equipment, the roof work by others or a specific energy output. New parts carry applicable manufacturer coverage under its own terms. |
| Energy and photos | No verified monthly production, electrical usage, utility bill offset or matched project photos are presented. Adding panels does not by itself establish how much more energy a system makes. |
If a roof repair and a solar expansion need to happen together, ask for a scope that identifies what will be reused, who sets the roof handoff date, and how the installer will document system operation before and after the work.
Ask about removing or reinstalling your solar panelsSource: Anonymized August 2026 The Metal Roofers signed agreement and two paid invoices. The location and customer details have been omitted. Historical project scope and cost, not a current quote.
The original $7,950 quote kept the array at 15 panels
The historical estimate was $7,950 to remove and reinstall the same 15 modules. It included new racking footings, reconnecting existing wiring and conduit, and a certified test before and after. It did not include new modules. The later $8,925 paid scope above included five additions. The old estimate was a separate option for the same roof work, not a second invoice or an insurer approval.