Knoxville, Tennessee · Historical commercial roof and solar proposals
Three roof options for a Knoxville building with about 200 solar panels
A Knoxville commercial building had corrosion concentrated near purlins on part of an existing R-panel roof and an array of roughly 200 solar panels. Three proposals ranged from a short-term seam repair to a full roof replacement and solar reset. The prices stayed the same across archived revisions; the recommended option and some scope measurements changed.
- Existing array, not a new solar proposal
- About 200 panels
- Panels specified for removal, depending on roof scope
- 0, about 100, or about 200
- Alternative quote totals, not payments
- $38,750 to $268,890
What were the three prices for?
The June 15, 2026 estimate set offered three different ways to address rust and leaks around existing rooftop solar. These are alternative total packages, not line items to add together.
| Option | Roof work | Panels to move | Quoted price |
|---|---|---|---|
| 1. Seam and spot repair | Treat about 2,000 linear feet of problem seams and address roof openings, rust holes and failed fasteners in spots. Limited repair; no roof replacement. | Panels stay in place. | $38,750 |
| 2. Partial replacement and coating | Replace the rusted northwest roof panels and underlying insulation; apply a coating to the remaining scope. Revised versions differ on coating type and area. | Remove and return about 100 panels above the work. The remainder was generally intended to stay, subject to field access. | $167,890 |
| 3. Full replacement and insulation work | Replace the complete roof. New insulation was specified in the badly affected section; remaining insulation would be checked after tear-off and priced separately if needed. | Remove and return the full array, roughly 200 panels. | $268,890 |
Solar capacity was not being expanded. The packages with panel removal included professional de-energization, detachment, reset, reconnection and testing of the existing equipment. The options quote a combined roof-and-solar scope, not stand-alone reset prices.
The short-term repair carried no warranty in the reviewed versions. Replacement and coating terms were specified separately in the estimates, and the original PV equipment was not included in a new equipment warranty.
What changed between versions of the proposal?
The sources have the same three prices and amount of solar to move, but the documents do not agree on the material, area, or recommendation for the roof. No executed form establishes which version became final.
| Proposal version | Partial-replacement language | Recommendation in that version |
|---|---|---|
| Silicone version | Describes replacing about 8,750 sq. ft. of the northwest section and silicone-coating about 15,000 sq. ft. of remaining roof in Option 2. | Option 3, full replacement and array reset. |
| Acrylic version | Describes replacing approximately 8,400 sq. ft. with new 2-inch insulation in the affected section and applying acrylic coating over approximately 11,000 sq. ft. in Option 2. | Option 2, partial replacement and coating. |
| Two other archived copies | Print 110,000 sq. ft. for the remaining coating area. This conflicts with the other copies and was not treated as a verified measurement. | Also recommend Option 2; the actual area, product and chosen option remain unconfirmed. |
The full replacement scope also uses about 8,400 sq. ft. for the severely affected insulation area. That is the area identified in the estimate, not a measurement of the whole roof or a promise about how much insulation needed replacement after tear-off.
What would need to be agreed in writing?
| Item | Evidence |
|---|---|
| Payment | A blank acceptance page shows 33% at signing, 33% at material delivery if applicable, and 34% at completion. It does not show a confirmed option, accepted price or receipt. |
| Dates | The form was issued June 15, 2026, with July 15, 2026 expiration. These numbers are historical. |
| Solar timing and warranty | The existing array would need to be detached where required, protected and tested after return. No downtime, equipment output, final commissioning, measured generation or related warranty approval was verified. |
| Existing system or hidden roof issues | Hidden structural conditions and significant unanticipated electrical issues would need a written change order. The proposal does not establish the size, model or operating performance of the installed array. |
| Completion and media | No executed agreement, invoice, verified payment, final field measurement, project photo or chosen option was confirmed for this case. |
When you compare quotes for a roof with solar already installed, get the exact work zone and the count of panels to move. Require the proposal to say who will protect them, how long they will be offline and what the restart check will document.
Price the roof work and the solar reset together
Ask a contractor to document the failed area, the roofing needed beneath existing panels, how much of the array must move and where fees fall if the site conditions differ.
Ask about commercial roof and solar coordinationSource: Anonymized The Metal Roofers Knoxville estimate set, issued June 15, 2026, pp. 1–5 and blank acceptance page. Alternative scopes; no contract execution, payment or completed work claimed.

