The Solar Roofers · Signed commercial scope
59.4 kW commercial solar and Level 2 EV charging
The signed scope paired 110 rooftop solar modules with one Level 2 charging station, for $180,695. Deposit payment is documented. Installation, utility permission to operate and measured output are not verified.
- Signed total
- $180,695
- Commercial PV capacity
- 59.4 kW DC
- Deposit marked paid
- $36,139
The contract establishes the signed scope and price. The job ledger shows the deposit payment. It does not establish project completion, utility approval, metered production, final payment or current pricing. Property and customer identifiers have been removed.
What the original quote covered
| Item | Signed agreement scope | Contract amount |
|---|---|---|
| Grid-connected solar system | 110 Jinko JKM540M-72HL4-V modules rated at 540 W each (59.4 kW DC). Three SolarEdge SE17.3K-USR2IBNZ4 inverters rated 17.3 kW AC each, 208 V three-phase, 51.9 kW aggregate. Racking, integration, commissioning and testing in scope. | $178,200 |
| Level 2 EV charger | One 240 V charging station, supplied and installed. Charger brand and charge rate were not listed. | $2,495 |
| Mounting and backup | Complete rack for 110 modules, 170° azimuth and 20° slope. No battery storage or outage-backup scope. | Included solar mounting |
| Signed cash price | PV plus charger, before separately billed third-party fees. No tax credit was deducted from the signed amount. | $180,695 |
| Due milestone | Contract share | Amount due under contract |
|---|---|---|
| Signing and engineering | 20% | $36,139.00 |
| Equipment order | 45% | $81,312.75 |
| Installation completion | 30% | $54,208.50 |
| Commissioning and inspection | 5% | $9,034.75 |
The deposit invoice for $36,139 was marked paid in the job ledger on September 18, 2026. The remaining job balance was $144,556 when reviewed. No final payment, completion, commissioning or permission to operate was verified.
The contract included design, coordination of permit and interconnection applications, procurement, mounting and electrical integration, commissioning and inspection coordination. External permit, inspection and utility application or study charges were billed at cost unless written as included. Structural repairs, listed work beyond the connection points, civil or trenching work, optional monitoring subscriptions, battery storage, and EV circuits beyond approved plans were not included.
Production and bill model
The original estimate forecasts 86,017 kWh per year against 89,300 kWh of estimated annual facility use, roughly 96%. That makes it a production-to-use ratio, not the portion of each bill eliminated. The model says about 46% of solar energy would be used at the site as generated, with the rest modeled as exported. An export credit below the retail rate is one reason the same model projects about 51% bill reduction rather than 96%.
| Month | Forecast PV (kWh) | Estimated use (kWh) | Model bill before | Model bill after | Model bill difference |
|---|---|---|---|---|---|
| Jan | 5,510 | 9,000 | $1,222 | $828 | $394 |
| Feb | 5,269 | 10,500 | $1,422 | $1,044 | $378 |
| Mar | 7,148 | 6,000 | $822 | $311 | $511 |
| Apr | 8,205 | 6,200 | $848 | $250 | $598 |
| May | 8,411 | 6,000 | $822 | $236 | $586 |
| Jun | 8,789 | 6,500 | $888 | $247 | $641 |
| Jul | 9,056 | 8,000 | $1,088 | $424 | $664 |
| Aug | 8,775 | 9,000 | $1,222 | $610 | $612 |
| Sep | 7,075 | 7,500 | $1,022 | $506 | $516 |
| Oct | 7,089 | 7,200 | $982 | $475 | $507 |
| Nov | 5,478 | 6,000 | $822 | $433 | $389 |
| Dec | 5,213 | 7,400 | $1,008 | $625 | $383 |
| Printed annual | 86,017 | 89,300 | $12,168 | $5,989 | $6,179 |
The exact displayed rows sum to 86,018 kWh generated and 89,300 kWh estimated use; their annual proposal headline prints 86,017 and 89,300 kWh. Both the monthly figures and the annual line are preserved as printed. Figures are not meter readings.
The estimate used System Advisor Model 2020.02.29.r2, 15.9% total system losses, 2.5% inverter losses, no optimizer/shade loss or performance adjustment, and the stated array geometry. The historical financial model applied Huntsville Utilities GSA assumptions: $0.10/kWh energy, $0.04/kWh fuel adjustment, $21.70/month fixed and $0.02/kWh assumed DPP export rate. It used 4% annual energy-price increases and a 6.75% financial discount rate, without out-of-warranty replacement costs. Neither tariff eligibility nor export settlement was verified.
The geometry follows the original source chart; the proposal does not print exact interim amounts. The curve is a projection and does not verify income, actual bill savings or payback.
Original terms and what remains unverified
The signed agreement sets 10-year workmanship coverage for covered installation work, separate from manufacturer coverage. This differs from two years in the earlier model document; the signed terms govern this historical project. Its panel terms are 12 years product and 25 years performance, with separate manufacturer terms for other equipment. This is not a warranty offer for other projects.
The archived proposal projected $174,894 of total bill savings over 20 years, $5,801 less than the original cash scope. These model figures are not deal terms, measured results, a current tariff quote or payback advice. No incentive or tax-credit eligibility is claimed.
Source basis: signed seven-page commercial agreement, scope and exclusions on page 2 and prices and milestones on page 3; supporting six-page proposal, annual model on pages 1–2, monthly details on page 3, and cumulative chart on page 4; and the matching commercial job invoice ledger. Names, address, signatures, invoice identifiers and source links omitted.
The Solar Roofers · Site-specific designs
Compare a design for your own property
Start with a year of usage, the roof or ground space, and the equipment you want to run during an outage.
Talk with the solar teamSee more design examplesEarlier $178,200 solar-only proposal and modeled bills
The original $178,200 cash proposal covered the same 59.4 kW solar array and three SolarEdge inverters but did not include an EV charger or battery. It was valid through August 15, 2026. The later signed $180,695 agreement added the $2,495 charger; it is the same commercial project, not two contracts to add together.
| Item | Earlier PV-only proposal | Later signed scope and accompanying model |
|---|---|---|
| Device scope | 110 540 W JinkoSolar modules; 59.4 kW DC, 51.9 kW quoted aggregate AC; no EV charger or battery. | Same rated solar and inverter scope, plus one 240 V Level 2 charger. No battery. |
| Gross amount | $178,200 proposed | $180,695 signed, of which $178,200 is the solar scope. |
| Annual energy forecast and usage assumption | 86,017 kWh and 89,300 kWh | Same annual figures. |
| Modeled first-year bill after solar | $7,640 (reported $4,528 below baseline) | $5,989 (reported $6,179 below baseline) |
| Historical lifetime bill difference | $133,249 estimated | $174,894 estimated |
Output and the annual usage assumption were the same across both exports. The earlier model lists energy and fixed charges but no explicit export-credit rate; the later one labels about 46% on-site use and a $0.02/kWh modeled export rate. The archived files do not quantify the contribution of each changed input. The EV charger price does not explain the change in bill projection.
| Month | Forecast PV (kWh) | Estimated use (kWh) | Model bill before | Model bill after | Modeled difference as printed |
|---|---|---|---|---|---|
| Jan | 5,510 | 9,000 | $1,222 | $857 | $364 |
| Feb | 5,269 | 10,500 | $1,422 | $1,026 | $395 |
| Mar | 7,148 | 6,000 | $822 | $499 | $323 |
| Apr | 8,205 | 6,200 | $848 | $487 | $361 |
| May | 8,411 | 6,000 | $822 | $454 | $367 |
| Jun | 8,789 | 6,500 | $888 | $481 | $408 |
| Jul | 9,056 | 8,000 | $1,088 | $606 | $482 |
| Aug | 8,775 | 9,000 | $1,222 | $714 | $507 |
| Sep | 7,075 | 7,500 | $1,022 | $632 | $389 |
| Oct | 7,089 | 7,200 | $982 | $630 | $352 |
| Nov | 5,478 | 6,000 | $822 | $550 | $272 |
| Dec | 5,213 | 7,400 | $1,008 | $701 | $308 |
| Printed annual | 86,017 | 89,300 | $12,168 | $7,640 | $4,528 |
Displayed row sums are 86,018 kWh generation, 89,300 kWh use, $12,168 before, $7,637 after and $4,528 of printed differences. Small differences from the printed total are not silently corrected. Neither export establishes the facility’s actual bills, final interconnection or an incentive.
Earlier source basis: six-page PV-only PDF, pp. 1–2 for design and model inputs, p. 3 for the monthly model, p. 4 for gross quotation and original lifetime curve. May not reflect any accepted terms. The later signed agreement, deposit ledger and model remain separately identified.

